Question 14 Not yet answered Marked out of 2.00 Flag question Domose Inc. planned to use $150 of material per unit but actually used $147
Question 14 Not yet answered Marked out of 2.00 Flag question Domose Inc. planned to use $150 of material per unit but actually used $147 of material per unit, and planned to make 1,100 units but actually made 900 units The flexible-budget variance for materials is Select one: a. $3,300 favorable b. $3,300 unfavorable C. Zero d. $2,700 favorable e. $2,700 unfavorable