Question 15 1.4 points Save Answer A project is expected to last 10 weeks. 5 weeks in, the project has an Earned Value of
Question 15 1.4 points Save Answer "A project is expected to last 10 weeks. 5 weeks in, the project has an Earned Value of $2000 and Planned Value of $3000. Based on this performance, what is the Schedule Forecast of the project? 15 weeks 10 weeks 5 weeks 20 weeks