Question 15 (2 points) Assume the following information: Actual run time this week Machine time available this week Actual run rate this week Ideal
Question 15 (2 points) Assume the following information: Actual run time this week Machine time available this week Actual run rate this week Ideal run rate Defect-free output this week 4,500minutes 5,000minutes 3.6units per minute 4.Ounits per minute 12,800units Total output this week (including defects) 16,200units The quality rate is closest to: 0.71 0.65 0.76 0.79