Question 15 Based on the chart below, some of the identified risks do not occur and therefore activity B gets done in 3 weeks. What
Question 15 Based on the chart below, some of the identified risks do not occur and therefore activity B gets done in 3 weeks. What is the effect on the project?
PM Chart X Activity Preceding Estimate Activity (weeks) Start 0 C Start D C C E D B AE F E End B.FStep by Step Solution