Question 16 A project whose critical path has an estimated time of 820 days with a variance of 225 has a 20% chance that
Question 16 A project whose critical path has an estimated time of 820 days with a variance of 225 has a 20% chance that the project will be completed before Note: Write answer in round figure 10 points Save Answer days? Question 17 5 points Save Answer A Water Dispenser manufacturing company produces water dispenser on an assembly line, currently producing 1,822 units per shift. If the production is increased to 2,932 units per shift. What is the percentage (%) increase in labor productivity. Note: Write answer in numerical rounded number. wwwwwww 13 points Save Answer Al Mashriq Furniture company makes handcrafted bed sets. The company makes 30,000 bed sets per month in year 2019 with the resources given in table. Calculate the multifactor productivity of Al Mashriq Furniture company. In year 2020 the compnay invested in machine which increased Capital Cost per month by 75% and also increased output by 78% per month. How much percentage productivity has improved at Al Mashriq Furniture company. Note: Write answer in round figure number only in the answer box. 16,421 @11 AED per hour Labor Hours per month Capital cost per month (AED) Raw Material per month (Kg) Energy cost per month (AED) 300,000 600,000@4 AED per kg 5,000
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started