Question 18 (4 points) The Project Funding Requirement Is generally higher than the cost baseline O Is generally about equal to the cost baseline O
Question 18 (4 points) The Project Funding Requirement Is generally higher than the cost baseline O Is generally about equal to the cost baseline O Is generally lower than the cost baseline O is the sum of the cost baseline and the earned value