QUESTION 18-construction finance GS construction is awarded a contract to build a commercial building. The contract price is $1,500,000 and during the first month of

QUESTION 18-construction finance

GS construction is awarded a contract to build a commercial building. The contract price is $1,500,000 and during the first month of the job, the following transactions occurred:

Cash expenditures to date

$300,000

Total expenditures to date

$350,000

Estimated expenditure to complete

$1,100,000

Total estimated expenditures

$1,450,000

Billing to date

$280,000

Cash collected to date

$250,000

What is "Revenue to Date" in Percentage of Completion Method? (select the closest one)

280,000

362,100

349,950

477,150

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Loose Leaf For Financial Accounting Fundamentals

Authors: John Wild, Ken Shaw, Barbara Chiappetta

6th Edition

1260151980, 978-1260151985

More Books

Students also viewed these Accounting questions