Question 19 Sunland has a standard of 2 hours of labor per unit, at $12 per hour. In producing 3000 units, Sunland used 5850 hours

image text in transcribed
Question 19 Sunland has a standard of 2 hours of labor per unit, at $12 per hour. In producing 3000 units, Sunland used 5850 hours of labor at a total cost of $71370. Sunland's labor price variance is O $1830 F. O $630 F O $1170 . 0 $300 U