Question 2 (10 Points) After 1 month, the progress of a project is reported as follows: Planned Completed Work 10% Actual Completed Work 5% Budget

Question 2 (10 Points)

After 1 month, the progress of a project is reported as follows:

Planned Completed Work 10%

Actual Completed Work 5% Budget Spent so far 15,000

Total Budget 100,000

A. Please calculate the following values (please show the formula and your work for each of the values for full credits (6 points): Budget at Completion (BAC) Earned Value (EV) Planned Value (PV) Actual Cost (AC) Cost Variance (CV) Schedule Variance (SV) Cost Performance Index (CPI) Schedule Performance Index (SPI) Estimate at Completion (EAC) Estimate to Completion (ETC) Remaining Work based on BAC Remaining Fund based on BAC

B. Please define To-Complete Performance Index (TCPI) in English (2 points) and calculate TCPI to meet the current EAC (please show formula and your work) (2 points)

image text in transcribed
Question 2 (10 Points) After 1 month, the progress of a project is reported as follows: Planned Completed Work 10% Actual Completed Work 5% Budget Spent so far 15, 000 Total Budget 100, 000 A. Please calculate the following values (please show the formula and your work for each of the values for full credits (6 points): Budget at Completion (BAC) Earned Value (EV) Planned Value (PV) Actual Cost (AC) Cost Variance (CV) Schedule Variance (SV) Cost Performance Index (CPI) Schedule Performance Index (SPI) Estimate at Completion (EAC) Estimate to Completion (ETC) Remaining Work based on BAC Remaining Fund based on BAC B. Please define To-Complete Performance Index (TCPI) in English (2 points) and calculate TCPI to meet the current EAC (please show formula and your work) (2 points)

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

The Economics Of The Energy Industries

Authors: William Peirce

2nd Edition

0275956261, 9780275956264

More Books

Students also viewed these General Management questions