QUESTION 2 ( 2 0 ?marks ) With reference to the table below, determine the activities that are on the critical path and the expected

image text in transcribed
QUESTION 2
( 2 0 ?marks )
With reference to the table below, determine the activities that are on the critical path and the expected time in which the project will be completed.
\ table [ [ Activity , Preceding, \ table [ [ Optimisti ] , [ cTime ] ] , Probable Time,Pessimistic Time ] , [ A , - , 7 , 1 0 , 1 9 ] , [ B , A , 2 , 2 , 8 ] , [ C , A , 8 , 1 2 , 1 6 ] , [ D , A , 3 , 5 , 1 0 ] , [ E , B , 4 , 6 , 8 ] , [ F , B , 6 , 8 , 1 0 ] , [ G , C , ?F , 2 , 3 , 8 ] , [ H , D , 2 , 2 , 1 6 ] , [ I , H , 6 , 8 , 1 4 ] , [ J , G , ?I, 4 , 6 , 8 ] , [ K , E , ?J , 2 , 5 , 4 ] ]
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

The Restaurant From Concept To Operation

Authors: John R Walker

7th Edition

1118629620, 9781118629628

More Books

Students also viewed these General Management questions

Question

Contrast Adlers and Freuds approaches to motivation.

Answered: 1 week ago

Question

for ( n = 0 ; n Answered: 1 week ago

Answered: 1 week ago

Question

The personal characteristics of the sender

Answered: 1 week ago

Question

The quality of the argumentation

Answered: 1 week ago