Question 2 (20 points). Redraw the following arrow diagram with bigger nodes (to include node number, ET, and LT;) and calculate early event time
Question 2 (20 points). Redraw the following arrow diagram with bigger nodes (to include node number, ET, and LT;) and calculate early event time (ET) and late event time (LT). Show critical path and critical activities. A B 6 A' 2 8 3 9 E J 6 5 F 4 7 H 6 2 7 D\5 5 G