Question

1 Approved Answer

QUESTION 2 ( 3 . 0 0 points ) Develop a resource schedule for the project network below. The project involves a which requires a

QUESTION 2(3.00 points)
Develop a resource schedule for the project network below. The project involves a which requires a team of programmers for its development. However, only 5 programmers are available.
Activity Subtitle
\table[[ES,ID,EF],[SLACK,RESOURCE,SLACK],[LS,DURATION,LF]]
Use the parallel method and the following heuristics to develop a schedule for the project: 1. Shortest slack. 2. Shortest duration. 3. Smallest identification number.
a) Present the project's workload. Report eventual resource overallocations. (1.50 point)
b) Present a new workload for the project. What is the new critical path and project duration after rescheduling the resources? (1.50 point)
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Transport Operations

Authors: Allen Stuart

2nd Edition

978-0470115398, 0470115394

More Books

Students also viewed these General Management questions