Question 2 a Five jobs, A, B, C, D, and E, arrives to be processed on the morning of January 1, 2021. PJC is scheduled

Question 2 a

Five jobs, A, B, C, D, and E, arrives to be processed on the morning of January 1, 2021. PJC is scheduled to work 7 days a week for the next 2 months. January's work for PJC consists of five jobs. A, B, C, D and E. Job A takes 3 days to complete and is due on day 9, job B takes 10 days to complete and is due on day 14, C takes 6 days to process and is due on day 8, job D takes 7 days to process and is due on day 14, and job E, which takes 5 days to process, is due on day 11.

Put together a FCFS, DDATE, SLACK, CR, SPT and a summary sequence for the above. (15 marks)

Job

Processing Time (days)

Due Date

A

3

January 9

B

10

January 15

C

6

January 8

D

7

January 14

E

5

January 11

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Information Technology Project Management

Authors: Kathy Schwalbe

6th Edition

978-111122175, 1133172393, 9780324786927, 1111221758, 9781133172390, 324786921, 978-1133153726

More Books

Students also viewed these General Management questions