Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

QUESTION 2 A network consists of the activities in the following list.Durations are given in weeks. What is critical path and completion time for this

QUESTION 2

A network consists of the activities in the following list.Durations are given in weeks. What is critical path and completion time for this project?

Activity Predecessor Duration
A - 8
B - 3
C A 7
D A,B 3
E C 4
F D 6

A.

Path: B-C-E, Duration: 17 weeks

B.

Path: A-D-E Duration: 17 weeks

C.

Path: A-D-E Duration: 19 weeks

D.

Path: A-C-E Duration: 19 weeks

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Holt McDougal Larson Geometry

Authors: Ron Larson, Laurie Boswell, Timothy D. Kanold, Lee Stiff

1st Edition

0547315171, 978-0547315171

More Books

Students also viewed these General Management questions

Question

Describe the steps in rational decision making.

Answered: 1 week ago

Question

What are the degrees of freedom associated with ????e.

Answered: 1 week ago