Answered step by step
Verified Expert Solution
Question
1 Approved Answer
QUESTION 2 A network consists of the activities in the following list.Durations are given in weeks. What is critical path and completion time for this
QUESTION 2
A network consists of the activities in the following list.Durations are given in weeks. What is critical path and completion time for this project?
Activity | Predecessor | Duration |
A | - | 8 |
B | - | 3 |
C | A | 7 |
D | A,B | 3 |
E | C | 4 |
F | D | 6 |
A. | Path: B-C-E, Duration: 17 weeks | |
B. | Path: A-D-E Duration: 17 weeks | |
C. | Path: A-D-E Duration: 19 weeks | |
D. | Path: A-C-E Duration: 19 weeks |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started