Question
Question 2: Based on the below project details, Prepare the project Network diagram (10 marks), Identify the Critical Path(s) and the expected time to complete
Question 2: Based on the below project details,
- Prepare the project Network diagram (10 marks),
- Identify the Critical Path(s) and the expected time to complete the project (5 marks)
- Find each activity's ES, EF, LS, LF and Total Slack and identify which activities has Free Slack (5 marks)
Activity | Duration (Days) | Dependency |
---|---|---|
Initial informational meetings | 5 | - |
Community mailing about construction project | 3 | - |
Marketing Workshops | 4 | Initial informational meetings |
Medical Center volunteer Workshop | 6 | Community mailing about construction project |
Create Community groups | 8 | - |
Medical Center staff Workshop | 6 | Initial informational meetings |
Presentation prepared for Speaker's Bureau | 4 | Marketing Workshops, Create Community groups |
Provide updates to community | 5 | Presentation prepared for Speaker's Bureau |
Inquiry log established | 5 | Create Community groups, Medical Center volunteer Workshop |
Ground-breaking ceremony | 12 | Provide updates to community |
Marketing plan developed | 10 | Inquiry log established |
PR firm contracted | 8 | Inquiry log established, Ground-breaking ceremony, Marketing plan developed |
Hire Marketing Director | 10 | Marketing plan developed |
Please explain it properly with steps so that I can understand in a better way
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started