Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

Question 2: Calculate Earned Value Indicators Basedon the following data: The Budget At Completion (BAC) cost of the project is estimated to be: $ 52,250

Question 2: Calculate Earned Value Indicators

Basedon the following data:

The Budget At Completion (BAC)cost of the project is estimated to be: $52,250.

  • Earned value data is available for the first three weeks of the project (see below).
  • The project is due to end on week four (4).
Project Data Week 1 Week 2 Week 3 Week 4
Cumulative Actual Costs $5,000 $16,000 $37,800
Cumulative Planned Value $11,750 $22,000 $43,000 $52,250
Cumulative Earned Value $7,000 $22,000 $47,000

Based on the above data, calculate the following earned value indicators:

EVM Indicator Week 1 Week 2 Week 3 Formula used
Cost Variance
Schedule Variance
Cost Performance Index
Schedule Performance Index

Estimated Cost At Completion

(use the EAC = BAC / CPI formula)

Estimated Cost to Complete

For this question you need to:

  • Identify which formulas you used for each indicator;
  • Show an example of your calculations (work) for each indicator; and
  • Calculate each indicator for each of the first three weeks.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Fundamentals Of Financial Management

Authors: Eugene F. Brigham, Joel F. Houston

Concise 3rd Edition

003033263X, 9780030332630

More Books

Students also viewed these General Management questions

Question

What laws have been passed to legislate ethics?

Answered: 1 week ago