Answered step by step
Verified Expert Solution
Question
1 Approved Answer
Question 2: Calculate Earned Value Indicators Basedon the following data: The Budget At Completion (BAC) cost of the project is estimated to be: $ 52,250
Question 2: Calculate Earned Value Indicators
Basedon the following data:
The Budget At Completion (BAC)cost of the project is estimated to be: $52,250.
- Earned value data is available for the first three weeks of the project (see below).
- The project is due to end on week four (4).
Project Data | Week 1 | Week 2 | Week 3 | Week 4 |
Cumulative Actual Costs | $5,000 | $16,000 | $37,800 | |
Cumulative Planned Value | $11,750 | $22,000 | $43,000 | $52,250 |
Cumulative Earned Value | $7,000 | $22,000 | $47,000 |
Based on the above data, calculate the following earned value indicators:
EVM Indicator | Week 1 | Week 2 | Week 3 | Formula used |
Cost Variance | ||||
Schedule Variance | ||||
Cost Performance Index | ||||
Schedule Performance Index | ||||
Estimated Cost At Completion (use the EAC = BAC / CPI formula) | ||||
Estimated Cost to Complete |
For this question you need to:
- Identify which formulas you used for each indicator;
- Show an example of your calculations (work) for each indicator; and
- Calculate each indicator for each of the first three weeks.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started