Question
Question 2. [Conduct Procurement, Vendor Selection] A project received proposals from a response to RFP and is in the decision process of selecting one vendor.
Question 2. [Conduct Procurement, Vendor Selection]
A project received proposals from a response to RFP and is in the decision process of selecting one vendor. The project selection committee agreed on the criteria and the weights of each criterion. Then, after detailed discussion of considerable information on each proposal, the project selection committee assigned a measure to each proposal for each criterion on a scale from 1 to 100 where higher is better.
Which proposal has the greatest unbiased weighted score based on the MCDM approach using the collected information from the RFPs?
A. Proposal A B. Proposal B C. Proposal C D. Proposal D E. Proposal E
Criteria | Weight | Proposal A | Proposal B | Proposal C | Proposal D | Proposal E |
C1. Technical approach | 40% | 40 | 90 | 40 | 80 | 40 |
C2. Management approach | 30% | 30 | 60 | 30 | 50 | 20 |
C3. Past performance | 20% | 50 | 20 | 20 | 40 | 10 |
C4. Price | 10% | 80 | 10 | 70 | 20 | 50 |
Sum | 200 | 180 | 160 | 190 | 120 |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started