Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

Question 2 Demonstrate understanding of Project Control Make a program / table to show a tunnelling program under the following conditions: There are two tunnelling

Question 2 Demonstrate understanding of Project Control Make a program / table to show a tunnelling program under the following conditions: There are two tunnelling machines (T1 and T2) that will bore from the same starting place to the end point. Their lengths are 2160m and 2348m respectively. T1 shall start 40 days before T2. They both shall proceed at the same rate of 8m/day. The tunnels need precast segment rings to be installed as they bore. The ring production schedule is 4 rings/day on a 6day/week basis. The precast segment ring is to be installed as the tunnelling machine bores the tunnel. Assuming that T1 starts on 1 Jan 2023, calculate:

(a) Completion dates for each of the machines. (8 marks)

(b) How many precast segment rings are required per tunnel (at 1.5m/ring)? (6 marks)

(c) Production time of the precast segment rings. (12 marks)

(d) Installation time of the precast segment rings (A minimal lag of 100m is to be maintained between tunnelling machine and the installation of the rings) (12 marks)

(e) When is the latest date to start the production of the precast segment rings in order to meet the tunnelling needs. Assume that the precast segment rings can be installed immediately after casting. (6 marks)

(f) The production of the precast segment rings is delayed due to some unforeseen circumstances. To catch up with the production, 2 additional moulds are made available on top of the 2 existing moulds. Analyse the impact to the completion date with this move. (6 marks)

references:

https://www.coursehero.com/u/file/198167573/BPM305-Study-Unit-1-2023pdf/

https://www.coursehero.com/u/file/198166506/BPM305-Study-Unit-2-2023pdf/

https://www.coursehero.com/file/198166544/BPM305-Study-Unit-3-2023pdf/

https://www.coursehero.com/u/file/198166756/BPM305-Study-Unit-4-2023pdf/

https://www.coursehero.com/u/file/198166502/BPM305-Study-Unit-5-2023pdf/

https://www.coursehero.com/u/file/198166542/BPM305-Study-Unit-6-2023pdf/

Step by Step Solution

3.45 Rating (148 Votes )

There are 3 Steps involved in it

Step: 1

To solve this problem lets break it down step by step Given data Length of tunnel for T1 2160m Length of tunnel for T2 2348m Both machines bore at 8md... blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Matching Supply with Demand An Introduction to Operations Management

Authors: Gerard Cachon, Christian Terwiesch

3rd edition

73525200, 978-0073525204

More Books

Students also viewed these General Management questions

Question

What is meant by planning or define planning?

Answered: 1 week ago

Question

Define span of management or define span of control ?

Answered: 1 week ago

Question

What is meant by formal organisation ?

Answered: 1 week ago

Question

What is meant by staff authority ?

Answered: 1 week ago