Question
Question 2 KSS common stock has a beta of 1.5. The market long-term expected return is 12% and the risk free rate is 2%. What
Question 2
KSS common stock has a beta of 1.5. The market long-term expected return is 12% and the risk free rate is 2%. What is the cost of retained earnings?
| 14% |
| 11% |
| 15% |
| 17% |
Question 3
CIS common stock currently pays a dividend of $2 per share and trades for $40 per share. New shares can be issued with a $2 per share floatation cost CIS is expected to grow at 4%. What is the cost of a new stock issue?
| 9.47% |
| 12.32% |
| 12.76% |
| 4.70% |
Question 4
KSS corporation uses 30% debt, 10% preferred stock, and 60% equity to finance new capital expenditures. The after tax cost of debt is 6%, the cost of preferred stock is 9%, the cost of retained earnings is 12% and the cost of a new stock issue is 14%. What is the WACC if a new stock issue is needed?
| 8.4% |
| 9.8% |
| 11.9% |
| 11.1% |
Question 5
Consider the following information for projects K and W:
Project K: NPV = $2,500 IRR = 20%
Project W: NPV = $1,500 IRR = 15%
Assume Project K and Project W are mutually exclusive projects with a WACC = 10%. Which of the following is true?
| Only Project W should be enacted since it has the highest NPV |
| Both Projects K and W should be enacted since both have a positive NPV |
| Only Project K should be enacted since it has the highest NPV |
| Neither Project K or W should be enacted since both have a positive NPV |
Question 6
Consider the following series of cash flows:
Cash Flow: -40 20 20 10 20
Time: 0 1 2 3 4
If you are using a 10% discount rate, which of the following is true?
| Payback will be smaller than discounted payback |
| Payback will be larger than discounted payback |
| Payback and discounted payback will both be less than 0 |
| Payback and discounted payback will be the same |
Question 7
A mining company is considering a new project. Because the mine has received a permit, the project would be legal; but it would cause significant harm to a nearby river. The firm could spend an additional $10 million at year 0 to mitigate the environmental problem, but it would not be required to do so. However, if the firm does not deal with the problem at year 0 they would face a lawsuit at the end of the project (year 4) at a cost of $20 million. Developing the mine (without mitigation) would cost $60 million and the expected cash inflows would be $20 million for 4 years. The weighted average cost of capital (WACC) is 12%. Below is a summary of possible outcomes:
NPV with mitigation costs at time 0 included = -$9.25 million
NPV without mitigation costs at time 0 and a lawsuit included in year 4 = -$11.96 million
Should the project be undertaken? If so, should the firm do the mitigation at time 0?
| Yes, the project should be undertaken and the mitigation expense should be conducted at time 0. |
| No, the NPVs are negative for every possible scenario. |
| Yes, the project should be undertaken and no mitigation should be conducted at time 0. |
| No, the WACC is too low. If the WACC was higher, then yes. |
Question 8
What is the NPV for the following series of cash flows is the WACC is 8%?
Cash Flow: -80 20 30 10 20 20
Time: 0 1 2 3 4 5
| $0.49 |
| -$2.82 |
| $20 |
| -$12 |
Question 9
KTS is trying to estimate the first-year operating cash flow. The financial staff has given you the following information:
Cost Savings = $12
Depreciation = $4
Interest Expense = $2
Marginal tax rate = 50%
What is the operating cash flow in year 1?
| $3.0 |
| $3.5 |
| $5.0 |
| $8.0 |
Question 10
Truman Industries is considering an expansion. The necessary equipment would be purchased for $12. The expansion would require an additional $2 investment in net operating working capital. The company spent and expensed $3 on research related to the project last year. What is the initial investment outlay for capital budgeting purposes?
| $12 |
| $11 |
| $17 |
| $14 |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started