Question
1 Approved Answer
Question 2 Sunshine Bhd. entered a contract to build a building for its customer with the agreed total price of $3,200,000. The project is expected
Question 2
Sunshine Bhd. entered a contract to build a building for its customer with the agreed total price of $3,200,000. The project is expected to last for 3 years with the total cost of $1,600,000. The following table shows the progress of the work:
| 31 Dec 2018 | 31 Dec 2019 | 31 Dec 2020 |
Completion (Market Value) | $950,000 | $2,600,000 | $3,200,000 |
Cost incurred to date | $400,000 | $1,000,000 | $1,600,000 |
Required:
- For each year, compute the recognized profit based on input method.
- For each year, compute the recognized profit based on output method.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started