Question
1 Approved Answer
Question 2 The information for a project is given in the Table below (time in weeks): Activity Immediate Activity predecessors time (t) A 8 B
Question 2 The information for a project is given in the Table below (time in weeks): Activity Immediate Activity predecessors time (t) A 8 B A 2 . 3 D A 60 E B 60 F 2 G D 2 H E, F 20 1 G 10 J H, 10 K J 12 L 3 a) Draw a network for this project b) Determine the critical path c) Determine the earliest and latest activity times d) Determine slack time for each activity
Step by Step Solution
There are 3 Steps involved in it
Step: 1