Answered step by step
Verified Expert Solution
Question
1 Approved Answer
QUESTION 2 With reference to the table below, determine the activities that are on the critical path and the expected time in which the project
QUESTION 2 With reference to the table below, determine the activities that are on the critical path and the expected time in which the project will be completed. Preceding Activity A B C D E F G H J A A A B B C, F D H G, I E, J Optimisti cTime 7 2 8 3 6 2 2 6 4 2 Probable Time 10 2 12 5 6 8 3 2 8 5 Pessimistic Time 19 8 16 10 8 10 8 16 14 8 (20 marks)
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started