Question 2 You are working on a Lean project. You have determined that you spend 120 minutes working through a refactoring of code and when you are finished you realized that it should have taken you 70 minutes. What is the current calculated process cycle efficiency? Select one O A. 70 minutes B. 30 percent O C. 120 Minutes O D. 36 percentQuestion 1 Please complete the following sentence with the answers below: is the total amount of time that the process takes, and is the total amount of time that an iteration takes. Select one 0 A. Cycle time, lead time 0 B. Lead time, cycle time 0 C. Velocity, sprint O D. Burn down, iteration Question 4 Which of the following Agile approaches are most compatible with each other? Select one 0 A. Scrum and XP 0 B. Scrum and Feature driven development 0 C. Large Scale Scrum and XP 0 D. XP and Crystal methods Question 3 As an Agile project manager, you recognize the value of looking back on an iteration and reviewing the performance as well as making plans for continuous improvements going forward. What kind of meeting would you facilitate in order to address all of those items? Select one Q A. Review 0 B. Postmortem O C. Retrospective O D. Premortem Question 6 The Theory of constraints is a study of which of the following? Select one O A. Work in progress (WIP) O B. Velocity improvements O C. Bottlenecks in the process O D. Cumulative flowWhich of the following could be considered a tailored or hybrid approach to Agile project management? Select one A. Kanban O B. ScrumBan O C. Scrumx O D. Large scale AgileQuestion 5 Which of the following organizations worked closely with the Agile Alliance to determine best practices of Agile in a predictive Waterfall environment? Select one 0 A. The Project Management Institute 0 B. The Scrum Alliance 0 C. The eXtreme Programming Alliance 0 D. Project managers globally Question 7 In the middle of your fourth iteration one of the developers requests a meeting to determine whether they should go in a different direction based on the code not passing the tests, when at this point in the process they should have. What kind of meeting is being requested? Select one Q A. Retrospective O B. Review 0 C. Standupmeeting O D. Intraspective Question 8 What is the best way to calculate throughput? Select one 0 A. Adding all the story points together and then dividing by the amount of iterations. O B. Adding all of the story points together and then multiplying by the amount of iterations O C. Adding all of the iterations together and then multiplying by the amount of story points 0 D. Adding all of the story points together and then dividing by the work in progress. Question 10 Which of the following is a correct statement based on lead time and velocity? Select one 0 A Teams that use velocity to track performance would want to increase velocity and, conversely, teams that use a Kanban approach would want to ' decrease their lead time. 0 B Teams that use velocity to track performance would want to decrease velocity, and conversely, teams that use a Kan ban approach would want to ' increase their lead time. 0 C Teams that use WIP to track performance would want to increase it to improve and teams that use a Kanban approach would want to decrease their ' lead time. 0 D Teams that use a Kanban to track performance would want to decrease velocity, and conversely, teams that use velocity approach would want to ' decrease their lead time