Question 20 (1 point) Consider a project with the following information. Crash cost per Activity Immediate predecessors Normal time Crash time period A 10
Question 20 (1 point) Consider a project with the following information. Crash cost per Activity Immediate predecessors Normal time Crash time period A 10 8 $180 B A 12 11 $300 C A 11 10 $150 D - 26 8 $260 E B, C What is the total cost of crashing the project by 2 time unit(s)? 5 3 $230