QUESTION 21 Hurren Corporation makes a product with the following standard costs: Inputs Standard Quantity or Hours Standard Price or Rate Standard Cost Per Unit

QUESTION 21

Hurren Corporation makes a product with the following standard costs:

Inputs

Standard Quantity or Hours

Standard Price or Rate

Standard Cost Per Unit

Direct materials

3.3 grams

$3.00 per gram

$9.90

Direct labor

0.8 hours

$12.00 per hour

$9.60

Variable overhead

0.8 hours

$9.00 per hour

7.20

The company reported the following results concerning this product in June.

Originally budgeted output

8,600

units

Actual output

8,500

units

Raw materials used in production

27,000

grams

Actual direct labor-hours

3,400

hours

Purchases of raw materials

30,700

grams

Actual price of raw materials purchased

$3.10

per gram

Actual direct labor rate

$12.90

per hour

Actual variable overhead rate

$8.70

per hour

The company applies variable overhead on the basis of direct labor-hours. The direct materials price variance is computed when the materials are purchased.

The materials price variance for June is: (Round your intermediate calculations to 2 decimal places.)

A.

$3,070 F

B.

$2,715 F

C.

$2,715 U

D.

$3,070 U

7 points

QUESTION 22

Landram Corporation makes a product with the following standard costs:

Inputs

Standard Quantity or Hours

Standard Price or Rate

Direct materials

2.0 kilos

$7.00 per kilo

Direct labor

1.3 hours

$17.00 per hour

Variable overhead

1.3 hours

$5.00 per hour

In March the company produced 4,500 units using 10,190 kilos of the direct material and 2,170 direct labor-hours. During the month, the company purchased 10,760 kilos of the direct material at a cost of $76,640. The actual direct labor cost was $38,249 and the actual variable overhead cost was $11,950.

The company applies variable overhead on the basis of direct labor-hours. The direct materials price variance is computed when the materials are purchased.

The materials quantity variance for March is:

A.

$8,330 F

B.

$8,330 U

C.

$8,476 U

D.

$8,476 F

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Agile Audit Transformation And Beyond

Authors: Toby DeRoche

1st Edition

1032062894, 978-1032062891

More Books

Students also viewed these Accounting questions