QUESTION 23 Landram Corporation makes a product with the following standard costs: Inputs Standard Quantity or Hours Standard Price or Rate Direct materials 2.0 kilos
QUESTION 23
Landram Corporation makes a product with the following standard costs: |
Inputs | Standard Quantity or Hours | Standard Price or Rate |
Direct materials | 2.0 kilos | $7.00 per kilo |
Direct labor | 1.4 hours | $10.00 per hour |
Variable overhead | 1.4 hours | $4.00 per hour |
In March the company produced 4,800 units using 10,320 kilos of the direct material and 2,300 direct labor-hours. During the month, the company purchased 10,890 kilos of the direct material at a cost of $76,770. The actual direct labor cost was $38,242 and the actual variable overhead cost was $11,943. |
The company applies variable overhead on the basis of direct labor-hours. The direct materials price variance is computed when the materials are purchased. |
The materials price variance for March is: (Do not round intermediate calculations.) |
A. | $540 F
| |
B. | $400 U
| |
C. | $400 F
| |
D. | $540 U |
7 points
QUESTION 24
Niemiec Corporation keeps careful track of the time required to fill orders. The times recorded for a particular order appear below: |
| Hour |
Move time | 2.3 |
Wait time | 19.3 |
Queue time | 11.4 |
Process time | 1.3 |
Inspection time | 0.9 |
The manufacturing cycle efficiency (MCE) was closest to: (Round your intermediate calculation and final answer to 2 decimal places.) |
A. | 0.02
| |
B. | 0.08
| |
C. | 0.92
| |
D. | 0.16 |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access with AI-Powered Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started