Question 24 Which of the following statements regarding PERT times is true? Select one: a. The optimistic time estimate is an estimate of the

image

Question 24 Which of the following statements regarding PERT times is true? Select one: a. The optimistic time estimate is an estimate of the minimum time an activity will require b. Most likely time estimate is an estimate of the maximum time an activity will require c. The optimistic time estimate is an estimate of the maximum time an activity will require d. Pessimistic time estimate is an estimate of the minimum time an activity will require e. The probable time estimate is calculated as t = (a + 4m + b).

Step by Step Solution

3.31 Rating (151 Votes )

There are 3 Steps involved in it

Step: 1

Option a The optimistic time estimate is an estimate of the minimum time an activity will require Ex... blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Financial Accounting

Authors: LibbyShort

7th Edition

78111021, 978-0078111020

More Books

Students also viewed these General Management questions