Question 27 1 pts Given the two projects with given cash flows, the NPV of project A is how many more or less use the
Question 27 1 pts Given the two projects with given cash flows, the NPV of project A is how many more or less use the negative sign if less) dollars than project B if the discount rate is 9%? Answer with two decimals. Project A Project B CFO: -14,748 -13,438 CF1: 3,225 1,974 CF2: 4,756 2,618 CF3: 9,547 4,643 CF4: 6,949 6,482 CF5: 2,156 12,224