Question
Question 27 At the end of June, the manager of the B.C. manufacturing plant was provided with the following variance analysis report. Budget Actual Variance
Question 27
At the end of June, the manager of the B.C. manufacturing plant was provided with the following variance analysis report.
Budget
Actual
Variance
Favourable (F)/
Unfavourable (U)
Production in units
320,000
338,00018,000FProduction costs:
Direct material$849,109$864,312$(15,203)UDirect labour
1,200,0001,238,760(38,760)
UVariable overhead costs
192,000201,313(9,313)
UFixed overhead costs
192,000189,2452,755FTotal production costs
$2,433,109
$2,493,630$(60,521)
U
The manager immediately called the production supervisor, demanding an explanation for the large unfavourable variance for the quarter. The production supervisor was puzzled. He thought the cost-cutting measures they had incorporated were beginning to work. He certainly wasn't expecting such a large discrepancy.
The standard rates the plant was using with its normal costing system are summarized below.
Volume
Cost
Direct material
1.10kg per unit
$2.40per kg
Direct labour
0.25hour per unit
$15.00
per hour
Predetermined overhead rate:
Variable
0.25hour per unit
$2.40per hour
Fixed
0.25hour per unit
$2.40per hour
Other relevant information:
1.A total of 379,000 kg of direct materials were purchased during the quarter at a cost of $2.50 per kilogram.2.A total of 360,130 kg of direct materials were used in production to manufacture 338,000 units.3.Payroll recorded 83,700 direct labour hours at an average cost of $14.80 per hour.
(a1)Calculate the following production variances and also the type of variance (favourable, unfavourable, neither)
Material price variance
Material quantity variance
Labour price variance
Labour efficiency variance
Variable overhead variance
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started