Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

Question 27 At the end of June, the manager of the B.C. manufacturing plant was provided with the following variance analysis report. Favourable (F)/ Unfavourable

image text in transcribed
image text in transcribed
Question 27 At the end of June, the manager of the B.C. manufacturing plant was provided with the following variance analysis report. Favourable (F)/ Unfavourable (U) Budget 306,000 Actual 323,000 Variance 17,000 Production in units Production costs: Direct material Direct labour Variable overhead costs Fixed overhead costs Total production costs $643,849 1,224,000 145,350 175,950 $2,189,149 $653,125 1,262,420 152,052 172,170 $2.239,767 $19,276) (38,420) (6,702) 3,780 (50.618) The manager immediately called the production supervisor, demanding an explanation for the large unfavourable variance for the quarter. The production supervisor was puzzled. He thought the cost-cutting measures they had incorporated were beginning to work. He certainly wasn't expecting such a large discrepancy. The standard rates the plant was using with its normal costing system are summarized below. Volume Cost Direct material 1.10 kg per unit $1.90 per kg Direct labour 0.25 hour per unit $16.00 per hour Predetermined overhead rate: Variable 0.25 hoor per unit $1.90 per hour Fixed 0.25 hour per unit $2.30 per hour Other relevant information: 1. 2. 3. A total of 363,000 kg of direct materials were purchased during the quarter at a cost of $1.95 per kilogram. A total of 343,750 kg of direct materials were used in production to manufacture 323,000 units. Payroll recorded 79,900 direct labour hours at an average cost of $15.50 per hour. (al) Calculate the following production variances. Material price variance Material quantity variance The manager immediately called the production supervisor, demanding an explanation for the large unfavourable variance for the quarter. The producon CODVISO WAS cost-cutting measures they had incorporated were beginning to work. He certainly wasn't expecting such a large discrepancy. HE The standard rates the plant was using with its normal costing system are summarized below. Volume 1.10 kg per unit $1.90 per kg 0.25 hour per unit $16.00 per hour Direct material Direct labour Predetermined overhead rate: Variable Fixed 0.25 hour per unit 0.25 hour per unit $1.90 per hour $2.30 per hour Other relevant information: 1. 2. 3. A total of 363,000 kg of direct materials were purchased during the quarter at a cost of $1.95 per kilogram. A total of 343,750 kg of direct materials were used in production to manufacture 323.000 units. Payroll recorded 79,900 direct labour hours at an average cost of $15.00 per hour. (1) Calculate the following production variances. Material price variance Material quantity variance Labour price variance Labour efficiency variance Variable overhead variance LINK TO TEXT LINK TO TEXT LINK TO TEST LINK TO TEXT LINK TO TEXT

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Auditing Concepts For A Changing Environment

Authors: Larry E. Rittenberg, Bradley J. Schwieger

5th Edition

0324223102, 978-0324223101

More Books

Students also viewed these Accounting questions