Question 3 0 of 4 8 An organization creates a scope / statement of work before designs are complete and some contract details are vague.
Question
of
An organization creates a scopestatement of work before designs are complete and some contract details are vague. What is a risk if the organization is using fixed price contracts?
The contractor may exercise the right to append the contract.
The contractor may need to be paid for more overtime.
The contractor may insist on a higher set hourly rate.
The contractor may pad hisher Estimates.