Question 3 ( 4 0 marks ) A . A PbS concentrate is produced by a rougher - cleaner flotation circuit. The cleaner tailings assay

Question 3
(40 marks)
A. A PbS concentrate is produced by a rougher-cleaner flotation circuit. The cleaner tailings
assay 15%PbS are recycled to the rougher cells, and the circulating load (recycle/fresh
feed) is 0.3. The fresh feed assays 10%PbS and is delivered at the rate of 1000 tons ?hr.
The recovery (PbS in cleaner concentrate ?PbS in fresh feed) and grade in the concentrate
are 95% and 85% respectively. What are the flow rates and assays of the other streams?
(15 marks)
B. A lead zinc mill treats 150 tons/day of ore assaying 8%Pb and 12%Zn and produced a
lead concentrate of grade 75%Pb,4%Zn and zinc concentrate of 55%Zn,1%Pb. The
tailing assay is 0.4%Pb and 0.8%Zn. How much Pb and Zn concentrates are produced in
the plant per day. [15.04 tons/day,30.11 tons/.
(15 marks)
C. Calculate how many kg of magnetite must be added to 1L of water to make a
slurry with a pulp density of 1.9gcm3. Assume density of magnetite is 5.2gcm3
(10 marks)
Answer all questions please
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Introduction To Chemical Engineering Thermodynamics

Authors: H.C. Smith, J.M. & Van Ness

2nd Edition

0070586993, 978-0070586994

More Books

Students also viewed these Chemical Engineering questions