Question
1 Approved Answer
Question 3 6 o f 4 8 What is typically true when assigning internal staff for the project team? Project managers request resources, but the
Question
What is typically true when assigning internal staff for the project team?
Project managers request resources, but the line managers decide whom to release.
Project managers are typically considered line managers and have the authority to acquire team members.
Parttime project team members with line responsibilities generally have no scheduling conflicts.
Project managers generally have no hiring authority.