Answered step by step
Verified Expert Solution
Question
1 Approved Answer
Question 3: (a) KANJAR Company is a manufacturer of light aircraft components in Oman. For the past two years of operation, the company is experiencing
Question 3: (a) KANJAR Company is a manufacturer of light aircraft components in Oman. For the past two years of operation, the company is experiencing production backlog. A number of its customers are complaining for long delays of deliveries. This backlog is hurting the competitive advantage and the profitability of the company. In order to address this issue, the operation manager decides to implement the following possible alternatives; production overtime, subcontracting, and possible hiring of additional workers if necessary. The company always prepares a nine-month aggregate plan to decide the optimum way to determine requirements for planning purposes, although this is modified when the demand requirements change. The estimated demand for a particular unit for the period January through September is given in Table Q3(a). The current workforce is based on the production level in the previous December. Operating data are given in Table Q3(b). Requirement: Develop an aggregate plan AP based on level capacity strategy specified for the planning period. Subcontract to meet a 100% service level every month and no overtime, no hiring, and no termination. Show graphically the demand forecast, actual production output, and ending inventory in single graph. Determine the total production cost for the specified period. m) Table Q3(c) shows the demand orders of aircraft component of a local customer from January to September. Develop a master planning schedule MPS, assuming production lot size of 800 units, and beginning inventory intended for the particular customer is 150 units. In your MPS indicate the projected available balance PAB and the MPS per month. [3] TableQ3(a): Veatch Company Estimated demand for a product Jan Mar April May June July August Sep 1,785 1,850 2,100 1,975 2,300 2,550 2,100 1,750 1,500 Feb Table Q3(b): Veatch Company Operating data Items Amount Initial inventory (units) 400 125 30 70 85 Stockout costs (OMR unit) Carrying cost, (OMR unit/month) Hiring cost per unit (OMR unit) Termination cost per unit (OMR unit) Subcontract cost (OMR unit) Production units the previous December In-house production cost, (OMR unit) Labor hours/ unit 85 1,500 75 3.2 40 Workweek (hours) Weeks/month 4 Jan Feb Table Q3(c): Veatch Company Operating data Mar April May June 400 500 550 600 July August Sep 350 400 650 700 750 Question 3: (a) KANJAR Company is a manufacturer of light aircraft components in Oman. For the past two years of operation, the company is experiencing production backlog. A number of its customers are complaining for long delays of deliveries. This backlog is hurting the competitive advantage and the profitability of the company. In order to address this issue, the operation manager decides to implement the following possible alternatives; production overtime, subcontracting, and possible hiring of additional workers if necessary. The company always prepares a nine-month aggregate plan to decide the optimum way to determine requirements for planning purposes, although this is modified when the demand requirements change. The estimated demand for a particular unit for the period January through September is given in Table Q3(a). The current workforce is based on the production level in the previous December. Operating data are given in Table Q3(b). Requirement: Develop an aggregate plan AP based on level capacity strategy specified for the planning period. Subcontract to meet a 100% service level every month and no overtime, no hiring, and no termination. Show graphically the demand forecast, actual production output, and ending inventory in single graph. Determine the total production cost for the specified period. m) Table Q3(c) shows the demand orders of aircraft component of a local customer from January to September. Develop a master planning schedule MPS, assuming production lot size of 800 units, and beginning inventory intended for the particular customer is 150 units. In your MPS indicate the projected available balance PAB and the MPS per month. [3] TableQ3(a): Veatch Company Estimated demand for a product Jan Mar April May June July August Sep 1,785 1,850 2,100 1,975 2,300 2,550 2,100 1,750 1,500 Feb Table Q3(b): Veatch Company Operating data Items Amount Initial inventory (units) 400 125 30 70 85 Stockout costs (OMR unit) Carrying cost, (OMR unit/month) Hiring cost per unit (OMR unit) Termination cost per unit (OMR unit) Subcontract cost (OMR unit) Production units the previous December In-house production cost, (OMR unit) Labor hours/ unit 85 1,500 75 3.2 40 Workweek (hours) Weeks/month 4 Jan Feb Table Q3(c): Veatch Company Operating data Mar April May June 400 500 550 600 July August Sep 350 400 650 700 750
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started