Question 3: Percentage of Completion Method (12 marks) On January 1, 2017, Eagle Construction Ltd. started a construction project for $4,500,000. Relevant data for 2017

Question 3:

Percentage of Completion Method (12 marks) On January 1, 2017, Eagle Construction Ltd. started a construction project for $4,500,000. Relevant data for 2017 and 2018 are as follows:

2017 2018

Current year construction costs$3,300,000$ 620,000

Estimated remaining costs to complete600,000-0-

Current year billings3,100,0001,400,000

Current year collections3,000,0001,500,000

Required: Calculate the following amounts for each method:

Completed Percentage-of Contract Completion2017201820172018

a) Gross Profit$$$$

b) Construction in progress year-end balance$$$$

c) Costs in excess of billings (Billings in excess of costs)$$$$

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Understanding Financial Accounting

Authors: Christopher D. Burnley

2nd Canadian Edition

1119406927, 978-1119406921

More Books

Students also viewed these Accounting questions