Question 3: Percentage of Completion Method (12 marks) On January 1, 2017, Eagle Construction Ltd. started a construction project for $4,500,000. Relevant data for 2017
Question 3:
Percentage of Completion Method (12 marks) On January 1, 2017, Eagle Construction Ltd. started a construction project for $4,500,000. Relevant data for 2017 and 2018 are as follows:
2017 2018
Current year construction costs$3,300,000$ 620,000
Estimated remaining costs to complete600,000-0-
Current year billings3,100,0001,400,000
Current year collections3,000,0001,500,000
Required: Calculate the following amounts for each method:
Completed Percentage-of Contract Completion2017201820172018
a) Gross Profit$$$$
b) Construction in progress year-end balance$$$$
c) Costs in excess of billings (Billings in excess of costs)$$$$
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started