Question 30 1.5 pts The specifications for a plastic liner for the concrete highway project calls for a thickness of 3.0 mm+0.1 mm. The standard
Question 30 1.5 pts The specifications for a plastic liner for the concrete highway project calls for a thickness of 3.0 mm+0.1 mm. The standard deviation of the process is estimated to be .02 mm. The process is known to operate at a mean thickness of 3.0 mm. What is the Cpk for this process? O 0.372 O 0.674 O 1.67 O None of the above