Question

...
1 Approved Answer

QUESTION 32 The following data pertain to operations at The Lego Group: Throughput Time Delivery Cycle Time Process Time Move Time. Inspection Time... Queue Time...

image text in transcribed

QUESTION 32 The following data pertain to operations at The Lego Group: Throughput Time Delivery Cycle Time Process Time Move Time. Inspection Time... Queue Time... 10 hours 14 hours 3 hours 4 hours 1 hour .2 hours The manufacturing cycle efficiency (MCE) for this operation would be: O a. 40% b.21.4% O c. 57.1% O d. 30%