Question 4 1 pts A future project has an uncertain finish time and the finish time follows a normal distribution. The project's expected finish time

image text in transcribed
Question 4 1 pts A future project has an uncertain finish time and the finish time follows a normal distribution. The project's expected finish time is 35 weeks, and the project variance is 9 weeks. If the project deadline is set to be 59 weeks, then what is the probability that the project would need more than the given deadline to complete? Input should be either 1 or 2. with 1 represents "more than 50%" and 2 represents "equal or less than 50%" 21

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Principles Of Managerial Finance

Authors: Lawrence J Gitman, Chad J Zutter

7th Edition

0133546403, 9780133546408

More Books

Students also viewed these Finance questions

Question

Describe the importance of global talent management.

Answered: 1 week ago

Question

Summarize the environment of recruitment.

Answered: 1 week ago