Question 4 1 pts Suppose you have the following project digraph. (The numbers in parenthesis represent hours.) STARHO) 0 . 30(0) Using the priority list
Question 4 1 pts Suppose you have the following project digraph. (The numbers in parenthesis represent hours.) STARHO) 0 . 30(0) Using the priority list F, E, A, D, B, G, C and the priority-list model to schedule this project with two processors, the project completion time is 17 hours. 22 hours. 18 hours. 21 hours. None of the above