QUESTION 4 A manufacturing plant has just completed a pilot run of 10 units of a major product and found the processing time for
QUESTION 4 A manufacturing plant has just completed a pilot run of 10 units of a major product and found the processing time for each unit was as follow: Unit number Time (Hours) 1 810 2 500 3 410 4 330 5 300 6 270 7 250 8 220 9 10 210 200 a. According to the pilot run, what would you estimate the learning rate to be? b. How much time would it take to produce the next 190 units, assuming no loss of learning? c. How much time would it take to make the 1000th unit?