Question

1 Approved Answer

Question 4 . Answer the following questions accorfing to the information given ia the table below. table [ [ Activity , Predeceseors,Durstion ( wevks

Question 4. Answer the following questions accorfing to the information given ia the table below.
\table[[Activity,Predeceseors,Durstion(wevks),Budget (S)],[A,-,6,900],[B,-,6,1200],[C,A,6,1200],[D,A,12,1800],[B,B,C,14,1400],[P,B,C,D,10,1500],[G,D,E,16,800]]
(20 poists) Deaw the Betwork with AOA (2O N is not evalua(cd). Find the critical path and the duration of the project.
4b.(15 points) At meck 24 of a project to shoot a TV commercial, what should the expenditures be? If the earned value is right on schedule but the actual expenses are $9,000, what are the cost atd rchedule variances? What are the EAC and the ETC?
BTC-EAC-AC:EAC-BACCPI;SV-BCWP-BCWS; V=BCWP-ACWP; CP-BCWPAC SPI-BCWP/BCWS
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Students also viewed these General Management questions

Question

Explain Methods for Setting the International Advertising Budget.

Answered: 1 week ago