Question 4 Bigwell construction has developed tasks duration and predecessor relationships in the following table for building model houses. The manager has been concerned with
Question 4
Bigwell construction has developed tasks duration and predecessor relationships in the following table for building model houses. The manager has been concerned with the amount of time it took to complete several jobs, some of the company workers are very unreliable. A list of activities and their optimistic completion time, the most likely time and the pessimistic completion time (in days) for a new contract are given in the following table.
Table 1.
Activity | Predecessors | Optimistic (a) | Most Likely (m) | Pessimistic (b) |
A | - | 1 | 2 | 3 |
B | - | 2 | 3 | 4 |
C | A | 4 | 5 | 6 |
D | B | 8 | 9 | 10 |
E | C,D | 2 | 5 | 8 |
F | D | 4 | 5 | 6 |
G | E | 1 | 2 | 3 |
A. Draw the activity network for this new contract (either AON or AOA). (4 marks) B. Determine the Expected Time and Variance for each activity. (4 marks) C. Show the activity schedule (ES, EF, LS, and LF) as well as slack (in table). (6 marks) D. Determine and state the critical path for this project. This MUST be based on your work in (C.) and not by inspection. (2 marks) E. What are the expected times and variances of the project? (2 marks) F. What is the probability the project will be finished within 20 weeks? (2 marks)
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started