Question 4 Giving the following information: Actual materials input used 8,500 KG Actual labor input used 3,500 hours Actual price of materials per unit $16

Question 4

Giving the following information:

  1. Actual materials input used 8,500 KG
  2. Actual labor input used 3,500 hours
  3. Actual price of materials per unit $16
  4. Actual price of labor per hour $10
  5. Flexible budget price of materials per unit $18
  6. Flexible budget price of labor per hour $8.5
  7. Flexible budget units of materials 8,000KG
  8. Flexible budget hours of labor 3,200 hours

Required:

  1. The price variance for both materials and labor
  2. The efficiency variance for both materials and labor.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Students also viewed these Accounting questions