Question 4 (Learning Curves) The Betta Kitchen Company (BKC) has been asked to bid for a contract to fit 600 identical kitchens into a number
Question 4 (Learning Curves)
The Betta Kitchen Company (BKC) has been asked to bid for a contract to fit 600 identical kitchens into a number of new apartment blocks. Because the kitchens to be fitted are different from anything that BKC has fitted before, they expect that a learning curve effect will take place.
The first kitchen is expected to take 24 labour hours to fit, and thereafter the time taken will be subject to a 95% learning rate. After 200 kitchens have been fitted, the learning effect will stop. The time taken for the 200th kitchen will also be the time taken for the remaining kitchens.
It is company policy to charge the following costs to each contract:
- Material costs. Materials for the contract are expected to cost 850 per kitchen, less a 5% bulk-buying discount.
- Labour. Labour costs for the contract will be 15 per hour.
- Overheads. Variable and fixed overheads are charged out per labour hour. Fixed and variable overheads for the year must be calculated using the High-Low method. Total overheads for the past four years have been:
Labour Hours worked Overhead cost (s)
Year 1 118,000 1,429,000
Year 2 125,000 1,480,000
Year 3 122,000 1,451,000
Year 4 115,000 1,400,000
The fixed overhead rate per labour hour to be charged to jobs should be calculated by taking the total fixed overhead figure calculated using the High-Low method, and dividing it by the average number of labour hours worked per year, over the past four years.
The final price to be quoted for the contract will be determined by adding a percentage mark-up to the total contract costs.
The learning factor for a 95% learning curve is -0.074
The learning curve formula is:
Yx = axb
Where:
Yx = average time per unit for x number of units
a = time taken for the first unit
b = the learning factor expressed as a decimal
x = cumulative output in units
N.B.: All learning curve calculations should be carried out to at least three decimal places
Required
1. Apart from the labour cost per hour and the overhead costs per hour, name SIX other important factors that BKC should take into account when calculating the final price to be quoted for the contract.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started