Question 4 The Steel Works, Inc. is required to carry a minimum of 40 days' raw steel, which is 250 tons. It takes 15 days
Question 4 The Steel Works, Inc. is required to carry a minimum of 40 days' raw steel, which is 250 tons. It takes 15 days between order and delivery. At what level of steel would Steel Works reorder? 1. 344 tons 3. 667 tons 600 tons 4, 3 750 tons