QUESTION 5 ( 2 0 Marks ) Using the data in the table below, create the project schedule using normal times. Determine the order in

QUESTION 5(20 Marks)
Using the data in the table below, create the project schedule using normal times. Determine
the order in which you would crash the project 1 day, 2 days, etc. until it is in an all crash
mode. Identify how much it would cost for each day you crash the schedule.
Activity Predecessor
Normal
time
Normal
cost
Crash
time
Crash
cost
Crash cost per
day
A B 52004350
B 82208220
C B 62504650
D A 95005600
E A,C 101509500
F E 105009650
G D,F 84006900

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Students also viewed these General Management questions

Question

Find fith). 4 4 1 14 Find fith). 4 4 1 14

Answered: 1 week ago