Answered step by step
Verified Expert Solution
Question
1 Approved Answer
Question 5 (8 marks) The following project has three independent paths as shown in the project network diagram. The deadline to complete this project is
Question 5 (8 marks) The following project has three independent paths as shown in the project network diagram. The deadline to complete this project is 46 days. Most B Optimistic Pessimistic Expected Variance Likely Activity Time Time Time of Time (days) (days) (days) Activity (days) Start D End A 10 16 28 B 20 28 42 30 42 E C 18 F D 15 15 15 E 1 2 3 F 42 45 48 a) What is the probability that this project will be delayed?b) What is the probability that activity:r F alone will take between 44 and 46 days
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started