QUESTION 5 (B) Footsteps company that manufactures shoes for children using a standard cost system. The standard production cost for a pair of shoes is
QUESTION 5 (B)
Footsteps company that manufactures shoes for children using a standard cost system. The standard production cost for a pair of shoes is as follows:
Cost | RM |
Direct material (2 meters @ RM4.50) | 9.00 |
Direct labor (0.5 hours @ RM16.00) | 8.00 |
Overhead Standard | 20.00 |
Total standard unit cost | 37.00 |
The total variable overhead for a flexible budget is RM11 per unit and the total fixed overhead is RM180000 per year. Expected production is RM40000 units. In 2015, the company produced 42,000 units. The costs involved for production in 2015 are as follows:
Cost | RM |
Direct materian (86000 @RM4.40) | 378400 |
Direct labour (20600 hours @16.10) | 331600 |
actual overhead | 416000 |
Total cost | 1126000 |
REQUIRED
a) Calculate the following variance:
i. Direct material price variance
ii. Direct material quantity variance
iii. Direct labor ladar variance
iv. Direct labor efficiency variance
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started