QUESTION 5 Given the following information, please answer question 5 to question 8 Activity Immediate Predecessors Completion Time ( Weeks ) A N / A

QUESTION 5
Given the following information, please answer question 5 to question 8
Activity
Immediate Predecessors
Completion Time (Weeks)
A
N/A
2
B
A
3
C
A
4
D
B
1
E
B,C
5
F
D
6
G
E
2
H
E
3
Q5. What are the latest start and the latest finish of the activity E?
Oa 8,13
b.11,16
c.16,21
Od.6,11
If activity B was delayed 3 weeks, what is the new total project completion time?
Group of answer choices
16
25
21
18
What is the critical path?
Group of answer choices
A, B, C, H
A, C, E, H
A, C, E, G
A, B, D, F
What is the total project completion time?
Group of answer choices
11
14
12
13

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Managing Information Technology

Authors: Carol Brown, Daniel DeHayes, Jeffrey Hoffer, Wainright Marti

7th Edition

132146320, 978-0132146326

More Books

Students also viewed these General Management questions