Question 5 (Mandatory) (1 point) A project leader has realized that two activities in the project cannot be done at the same time because not

image text in transcribed
image text in transcribed
image text in transcribed
Question 5 (Mandatory) (1 point) A project leader has realized that two activities in the project cannot be done at the same time because not enough resources are available. Activity 3 is critical and has a duration of 5 days. Activity 4 has 2 days of slack and a duration of 2 days. How will the project leader decide which activity should be scheduled first? The activity with the smallest duration The activity with the most slack The activity with the least slack The activity with the lowest identification number The activity with the highest cost Question 6 (Mandatory) (1 point) These are all guidelines a project manager should consider when assigning project work EXCEPT when possible, team veterans up with new hires. select people with compatible work habits and personalities. have people work together early so that they can become familiar with each other. select individuals with skillsets that complement each other. always assign the best people to the most difficult tasks. Question 31 (Mandatory) (5 points) Identify and give an example of the three types of resource constraints. Question 32 (Mandatory) (5 points) When do you know you have crashed project activities enough? In other words, when you are crashing a project, how do you know you are finished? AJ

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Nmap Network Exploration And Security Auditing Cookbook

Authors: Paulino Calderon

2nd Revised Edition

1786467453, 978-1786467454

More Books

Students also viewed these Accounting questions

Question

What is the orientation toward time?

Answered: 1 week ago

Question

4. How is culture a contested site?

Answered: 1 week ago